57th Construction day (loft)
main event of the day the completion of the "Blue Room". It's been wonderful. ;-)))
now expected, the temperature fluctuations up there something to be mitigated.
Unfortunately I made a picture from the window. This fact has been framed very nicely. I ran after. The guys from Wendt have once again great job. This was all cleaned up and swept, is there already almost taken for granted. (Unfortunately the light was tempered ...)
to yesterday's events:
landscaping - we are excited about the offer ...
heating instruction - good Goodness. That was beyond my capacity at some point. 30 minutes pure information. Please let the part run automatically ...
parquet layers - who took care of some disappointment. No, it was not because of him. Quite the contrary. But the ground is at 2.4% CM clearly too wet. We have to make a new measurement next week. The heating program of the FBH is now back in full swing (and our electricity meters also ...). Then, still found that the door frames are much too high (7-8mm). :-( Hopefully Viebrock gets the further correction. Especially in transition tile to hardwood floor is likely to be difficult. Because we are a bit nervous about whether there is a happy end.
Electrical - in terms of home automation is now awarded the contract and ordered all -> it is the budget version: HOME MATIC . We are curious how it will work. On
8.11. but at least now we get our garbage cans. That's also what.
Now we hope mainly that the artist gets going ... (Our wallpaper is in fact arrived)
Thursday, October 28, 2010
Tuesday, October 26, 2010
Buy Glucocimine In India
55th Construction day (preliminary acceptance)
Today was the pre-acceptance . Everything went smoothly; really like the "normal" BL-call each week.
course, there were a few points. All just little things that probably no problem to the final inspection at 1.11. (For us was moved to the back) will be done.
example, there were a few small cracks in the plaster, a Katsche in the country, sitting crooked exhaust pipe, etc. In addition, the
sealer was in and around the house go. Specifically, the joint super-class from the outside see n - which are indistinguishable from the mortar-joints. Perfect!
was also now the final electrical instead. Also ran without problems - 2 insignificant details were still open.
came to top it all a Lord of Glamü and measured, the shower. Very encouraging was that the glass walls not 7-8 weeks delivery time as Wendt specified, but only have 3 weeks. Phew. So the issue deserves to be done soon after our arrival.
Oh yes, MEDA was also the delivery of our kitchen nteile fixed. They come a day before our move. Wonderful. Fortunately, today was
swept our house by Viebrock and the tiles and windows (including frame) but were cleaned thoroughly. Super service! The difference to before is clearly visible. A fine thing. ;-)
morning are several important dates: 1st
Meeting with a builder regarding outdoor gala planning
second Heating training
third CM measurement of the floor through the fourth floor Leger
Meeting with a new electrician regarding home automation
Everything in the half-hour in the evening ....
Today was the pre-acceptance . Everything went smoothly; really like the "normal" BL-call each week.
course, there were a few points. All just little things that probably no problem to the final inspection at 1.11. (For us was moved to the back) will be done.
example, there were a few small cracks in the plaster, a Katsche in the country, sitting crooked exhaust pipe, etc. In addition, the
sealer was in and around the house go. Specifically, the joint super-class from the outside see n - which are indistinguishable from the mortar-joints. Perfect!
was also now the final electrical instead. Also ran without problems - 2 insignificant details were still open.
came to top it all a Lord of Glamü and measured, the shower. Very encouraging was that the glass walls not 7-8 weeks delivery time as Wendt specified, but only have 3 weeks. Phew. So the issue deserves to be done soon after our arrival.
Oh yes, MEDA was also the delivery of our kitchen nteile fixed. They come a day before our move. Wonderful. Fortunately, today was
swept our house by Viebrock and the tiles and windows (including frame) but were cleaned thoroughly. Super service! The difference to before is clearly visible. A fine thing. ;-)
morning are several important dates: 1st
Meeting with a builder regarding outdoor gala planning
second Heating training
third CM measurement of the floor through the fourth floor Leger
Meeting with a new electrician regarding home automation
Everything in the half-hour in the evening ....
Monday, October 25, 2010
Chicken Broth In A Can Expired?
54th Construction day (blower door test)
Today was the blower door test done ...... and of course passed. ;-)
The masons our future home have also visited, while the garage door with "strap" provided. Still it looks a little funny, because the joints were not made and seems to match the white garage wall.
We eagerly toward the completion of this already and are in terrible stress with respect to wallpaper, paint, window "blinds", planning the outdoor facilities, etc.
this wallpaper, we have ordered for the bedroom:
wallpaper VI probably not give it - instead, we will "colorize" the painter fleece ...
Today was the blower door test done ...... and of course passed. ;-)
The masons our future home have also visited, while the garage door with "strap" provided. Still it looks a little funny, because the joints were not made and seems to match the white garage wall.
We eagerly toward the completion of this already and are in terrible stress with respect to wallpaper, paint, window "blinds", planning the outdoor facilities, etc.
this wallpaper, we have ordered for the bedroom:
|
| Hermitage is more Satin AS Creation |
Sunday, October 24, 2010
Chelsea Charm At Home
24.10.2010
We have a new kitchen!
My father had announced some time ago to try to fund our kitchen. On Tuesday I talked to him and him from the previous planning status reports. He was of the opinion that it would then now is the time to go to several furniture stores in order to obtain offers. On Saturday, we wanted to start again with it, as we present the installation plans even to the sampling should have. Well, compare the prices never happened, because in the first store they made my father for him apparently quite acceptable offer, so that he signed the contract directly. After that we enjoyed even at the expense of the store for lunch and a toast to the new kitchen. At least we have you ever have one less worry, even if our beautiful kitchen coupon not now but will be used. Now we are just waiting for the sampling date!
When it comes to property we were not idle in our holiday, even though we are not able to come this far in advance as intended. But those who have the Raspberry bushes can remember, I would say, that they belong to the past since Wednesday. Stephan has toiled pretty hard to rauszubekommen out the bushes and the cast (!) Trellis. Now have "only" the tree roots, the currants and raisins out, and then the civil contractors come to the excavation!
We have a new kitchen!
My father had announced some time ago to try to fund our kitchen. On Tuesday I talked to him and him from the previous planning status reports. He was of the opinion that it would then now is the time to go to several furniture stores in order to obtain offers. On Saturday, we wanted to start again with it, as we present the installation plans even to the sampling should have. Well, compare the prices never happened, because in the first store they made my father for him apparently quite acceptable offer, so that he signed the contract directly. After that we enjoyed even at the expense of the store for lunch and a toast to the new kitchen. At least we have you ever have one less worry, even if our beautiful kitchen coupon not now but will be used. Now we are just waiting for the sampling date!
When it comes to property we were not idle in our holiday, even though we are not able to come this far in advance as intended. But those who have the Raspberry bushes can remember, I would say, that they belong to the past since Wednesday. Stephan has toiled pretty hard to rauszubekommen out the bushes and the cast (!) Trellis. Now have "only" the tree roots, the currants and raisins out, and then the civil contractors come to the excavation!
Thursday, October 21, 2010
Pokemon Silver And Gold For Mac
51st Construction day (Plumbing done)
Today, the farmer heating and plumbing total finished.
We revel in the corresponding visual delight of our valves. ;-)))
But see yourself ..
We are always more on the completion of construction and our catchment. * Hop *
Otherwise, nor were the lack of French balconies on the west side delivered and installed. The also look great.
Otherwise, today was the owner in EL on the move:
The boxes in Terminal cinema room were connected and mounted.
How you go see it step by step towards completion.
The Electricians must still complete his stuff - but even that will slowly become less. The sealer
must accomplish his work, and then there are some little things ...
morning, I can bring back the inner tube. ;-)
The Baustromkasten was already last week reduced.
I was so slow even order garbage cans ... * Node *
ear (so slow getting serious ...)
Today, the farmer heating and plumbing total finished.
We revel in the corresponding visual delight of our valves. ;-)))
But see yourself ..
|
| here only has the keeper for you mounted hand shower ... |
|
| submerged thermostat |
|
| The Construction Project Owner pride ;-)) |
|
| the "soft closing" has to be cool ... |
Otherwise, nor were the lack of French balconies on the west side delivered and installed. The also look great.
Otherwise, today was the owner in EL on the move:
The boxes in Terminal cinema room were connected and mounted.
How you go see it step by step towards completion.
The Electricians must still complete his stuff - but even that will slowly become less. The sealer
must accomplish his work, and then there are some little things ...
morning, I can bring back the inner tube. ;-)
The Baustromkasten was already last week reduced.
I was so slow even order garbage cans ... * Node *
ear (so slow getting serious ...)
Wednesday, October 20, 2010
Improve fm Transmitter
50th Construction day
"tiles ready!"
describes the construction day today's probably accurate.
The bathroom tiles were the last things today. Everything looks perfect. The broken tile on the tub, of course, was also renewed.
We are excited about what Thu & Fri yet happened. Because we want to take place Monday, the pre-acceptance.
"tiles ready!"
describes the construction day today's probably accurate.
The bathroom tiles were the last things today. Everything looks perfect. The broken tile on the tub, of course, was also renewed.
We are excited about what Thu & Fri yet happened. Because we want to take place Monday, the pre-acceptance.
What Are Some Illegal Bats In Softball
20.10.2010
kitchen design, here we come!
After we have submitted the planning application now, it's time, once already to address the kitchen planning. So we were yesterday and the day before in a couple of furniture stores in order to give us first impressions (and initial offers). Yesterday we then find anything and now have a pretty good idea of what our future kitchen should be. Now it depends only on the right offers.
kitchen design, here we come!
After we have submitted the planning application now, it's time, once already to address the kitchen planning. So we were yesterday and the day before in a couple of furniture stores in order to give us first impressions (and initial offers). Yesterday we then find anything and now have a pretty good idea of what our future kitchen should be. Now it depends only on the right offers.
Tuesday, October 19, 2010
How To Play Boutique Monopoly
49th Construction day (doors)
Hi, longer nothing heard / read, right?
Well, we are somewhat in the run-and-stress at the site was not sooo much going on. mounted
But today the doors and baseboards been. It all looks very chic. surprised at the baseboards me but the distances to wall in some places of 1-2mm. This does not look as good. I'm going to ask the BC ...
In Bad now the Squaro has arrived - now it can go as well.
Well, since it takes ages to arrive, the shower wall - it must be measured so first of all - we are in the shower probably have no benefit in 2010. :-(((
The shock to the building owner was as follows:
had not been "dismantled" the only fitting the quasi - also is also the cleanest cut tile that is broken * * Sniff.
Well, what is now on / off?
- The electrician has removed all but switch / plug, as not dull. But the mats are not yet delivered. The rack is still not corrected, the lights do not work outside in front of the kitchen and the bathroom are spots still do not know. -Hmpf
- The Services people have to do it very well - toilets and faucets are not hung up / connected.
- The tile in the bathroom must have ran.
- The French balconies missing rear.
- Some shutters missing the limiter, some not clean run ... interests must still be adjusted.
- The door handle of the door will come.
- The wood railing has a Macke: - /
- The Master- sealer is still and will make a perfect job (with one operand for the outer joints)
- blower door test
is with us still out:
- have with the Gala-Bauer - comes from Wednesday probably the painter and starts
- Next week, the parquet layers
- Right after the fireplace specialist
- There comes hopefully by 1 & 1 in the corridors
we discuss the steps outside
- garbage cans must be ordered (so far the city has not responded to my emails)
- The will loft insulation needs - here I still hope to our BL (Help!)
- We must make further choose wallpaper in the bedroom ...
Next Week is preliminary and final inspection. Since VB has a lot to be done before, but it works already. On 16./17.11. we want to move - this all looks very good. ;-)
Hi, longer nothing heard / read, right?
Well, we are somewhat in the run-and-stress at the site was not sooo much going on. mounted
But today the doors and baseboards been. It all looks very chic. surprised at the baseboards me but the distances to wall in some places of 1-2mm. This does not look as good. I'm going to ask the BC ...
we are very satisfied with the doorknobs - especially those the bathroom / WC-G. ;-)
Well, since it takes ages to arrive, the shower wall - it must be measured so first of all - we are in the shower probably have no benefit in 2010. :-(((
The shock to the building owner was as follows:
had not been "dismantled" the only fitting the quasi - also is also the cleanest cut tile that is broken * * Sniff.
Well, what is now on / off?
- The electrician has removed all but switch / plug, as not dull. But the mats are not yet delivered. The rack is still not corrected, the lights do not work outside in front of the kitchen and the bathroom are spots still do not know. -Hmpf
- The Services people have to do it very well - toilets and faucets are not hung up / connected.
- The tile in the bathroom must have ran.
- The French balconies missing rear.
- Some shutters missing the limiter, some not clean run ... interests must still be adjusted.
- The door handle of the door will come.
- The wood railing has a Macke: - /
- The Master- sealer is still and will make a perfect job (with one operand for the outer joints)
- blower door test
is with us still out:
- have with the Gala-Bauer - comes from Wednesday probably the painter and starts
- Next week, the parquet layers
- Right after the fireplace specialist
- There comes hopefully by 1 & 1 in the corridors
we discuss the steps outside
|
| The patch would please us very good front ... |
- The will loft insulation needs - here I still hope to our BL (Help!)
- We must make further choose wallpaper in the bedroom ...
|
| This should (in our opinion) a beautiful ornate, dark , wrought iron bed fit |
Next Week is preliminary and final inspection. Since VB has a lot to be done before, but it works already. On 16./17.11. we want to move - this all looks very good. ;-)
Thursday, October 14, 2010
Bow Legs Pilates Ring
45th Construction day (heating)
Today, there were not sooo many new things, as in recent days. It
the heating or the split unit was installed. The device is certainly not an optical enrichment of our house. ;-)
We will probably cover up later with grasses / bamboo. We wanted before planting in the front yard.
lies in the part probably not just a "fan", but plenty of art.
mounted or otherwise of the basin in the bathroom
and-very important-it continued to work on the bathtub faucet. Today one can not detect in him the progress. * Fanfare *
Today, there were not sooo many new things, as in recent days. It
the heating or the split unit was installed. The device is certainly not an optical enrichment of our house. ;-)
|
| Super, also set to NEN mega base ... |
|
| This cover sheet looks somehow not ready for ... |
We will probably cover up later with grasses / bamboo. We wanted before planting in the front yard.
lies in the part probably not just a "fan", but plenty of art.
|
| Herz-/Lungenmaschine fan at the ... lol was |
mounted or otherwise of the basin in the bathroom
and-very important-it continued to work on the bathtub faucet. Today one can not detect in him the progress. * Fanfare *
Wednesday, October 13, 2010
Do Pinguecula Go Away?
44th Construction day (garage)
Today, everything was marked by the garage.
This has all worked out great. Rekers is - especially in the perfect cooperation with Viebrock - for a clear recommendation. Unique, that the very clear electrical connection was not made by Rekers, surprised me.
way: This is what our new eHZ of:
Somehow I can not write comments anymore, since the drop-down box, no account is selected. : - / Sorry. Neither can I write in what other blogs - even here to respond to the many nice comments. No idea why. :-(
|
| First, the growing ... |
|
| High fascinating to see how the arm is part of mm-positioned exactly |
|
| then comes the actual Garage |
|
| and is accurately to the growing set |
from finished Here we go:
|
| The front is still faced with straps of our clinker. |
way: This is what our new eHZ of:
|
| it goes anyway ... ;-) |
Somehow I can not write comments anymore, since the drop-down box, no account is selected. : - / Sorry. Neither can I write in what other blogs - even here to respond to the many nice comments. No idea why. :-(