55th Construction day (preliminary acceptance)
Today was the pre-acceptance . Everything went smoothly; really like the "normal" BL-call each week.
course, there were a few points. All just little things that probably no problem to the final inspection at 1.11. (For us was moved to the back) will be done.
example, there were a few small cracks in the plaster, a Katsche in the country, sitting crooked exhaust pipe, etc. In addition, the
sealer was in and around the house go. Specifically, the joint super-class from the outside see n - which are indistinguishable from the mortar-joints. Perfect!
was also now the final electrical instead. Also ran without problems - 2 insignificant details were still open.
came to top it all a Lord of Glamü and measured, the shower. Very encouraging was that the glass walls not 7-8 weeks delivery time as Wendt specified, but only have 3 weeks. Phew. So the issue deserves to be done soon after our arrival.
Oh yes, MEDA was also the delivery of our kitchen nteile fixed. They come a day before our move. Wonderful. Fortunately, today was
swept our house by Viebrock and the tiles and windows (including frame) but were cleaned thoroughly. Super service! The difference to before is clearly visible. A fine thing. ;-)
morning are several important dates: 1st
Meeting with a builder regarding outdoor gala planning
second Heating training
third CM measurement of the floor through the fourth floor Leger
Meeting with a new electrician regarding home automation
Everything in the half-hour in the evening ....