31.01.2011
sampling Day 1
After only 6 hours of sleep and an approximately 2-hour drive we arrived at 9.00 clock on at the company Finger house in Frankenberg. After a brief welcome and by speaking of the process, we plunged immediately searching for a wall color, roof tiles, roof beams, roof tiles etc. While this was both of us very quickly from Amsterdam, it was at the interior doors more difficult and our peak we reached after dinner when selecting the sanitaryware and wall and floor tiles. When we felt that after 2 hours finally behind We had, then came the disappointment: We did not really read the description of construction work and have forgotten that the house price is only the wall tiles of the object in the guest bathroom is included. If we want the whole (2.14 square meters!) WC is tiled up to the side walls 1,60 m, this means additional cost of 700 € for us.
was after this information, the next bad news was not long to: Our considerations for the design of the air in our controlled ventilation were found to be not feasible, which was particularly annoying because we in the run with a finger house staff had discussed using a model house.
After a long and very hard day for us but we are now sitting comfortably in the Pension Eder beach and let the day's events. Although we were convinced at the beginning of being able to live well with the standard objects, but now have additional costs arising in the five-figure range, we first have to think in peace.
All in all, the day today but was very positive and we look forward to the 3D view of our bathrooms, which we will start tomorrow morning. Now we go to bed but only once. Such a Bemusterungstag is in fact really hard!
Oh yeah, almost I had forgot:
According to current projections, our house is but already in the 20th KW, ie, in the week of 16 - 20.05.!
Monday, January 31, 2011
Friday, January 28, 2011
Shop Security Tags Metal
28.01.2011
Finally back hard in the planning
with us long after nothing happened, we are now totally on the sampling date. Since the beginning of the week we sit every evening at home and brood over the furniture plans. Today we have once again intensely preoccupied with the experience of other builders in the sample. It is huge, how many things we have to observe. And then the uncertainty of whether we are behind them in what we have planned and decided, really happy in the long run. I hope that finger house manages to take us during the sampling of expert advice on track at our insecurities!
Finally back hard in the planning
with us long after nothing happened, we are now totally on the sampling date. Since the beginning of the week we sit every evening at home and brood over the furniture plans. Today we have once again intensely preoccupied with the experience of other builders in the sample. It is huge, how many things we have to observe. And then the uncertainty of whether we are behind them in what we have planned and decided, really happy in the long run. I hope that finger house manages to take us during the sampling of expert advice on track at our insecurities!
Saturday, January 15, 2011
Bridal Shower Poems For No Registery
15.01.2011
Yay, it goes on!
is now eight weeks after it finally stopped on * happy * Yesterday, an employee of the company called finger house and with us denied the sampling date. The sampling will take place on 01.31 and 01.02. instead.
Today we travel again to our kitchen studio, because we have the position of the center block, but their mind otherwise. I hope it's not a big deal to reschedule these programs, but it really would have to go quite quickly, as we had nothing in the actual equipment change the kitchen, but only the position (40 cm to the left).
Yay, it goes on!
is now eight weeks after it finally stopped on * happy * Yesterday, an employee of the company called finger house and with us denied the sampling date. The sampling will take place on 01.31 and 01.02. instead.
Today we travel again to our kitchen studio, because we have the position of the center block, but their mind otherwise. I hope it's not a big deal to reschedule these programs, but it really would have to go quite quickly, as we had nothing in the actual equipment change the kitchen, but only the position (40 cm to the left).
Thursday, January 6, 2011
Western University Of Health Sciences Review
Monday, January 3, 2011
License Plate Bracket 08 Honda Civic
Conclusion
Viebrock:
happy again at any time! Very happy with Mr. Biesen, our consultant in Kaarst. Very happy again with Mr. Löhden, our construction manager. stress-free as we can with Viebrock, not build it, I say. The construction period
is phenomenal. The quality is great - if we as the layman can judge at this time. Any trouble and when it is going to be resolved were issues, so these were done without a lot of discussion of Viebrock. Great support from Viebrock - even after acceptance (at least so far). The architects are part of the process must clearly high -
: *
suggestions for Viebrock. We were there just before the contract cancellation.
- The heating instruction should include a brief pamphlet in which the 10 most important points are summarized. The components of the heaters are indeed quite uniform and thus the cost of Viebrock clear. The benefit would be our opinion but high.
- It would be great if Viebrock for the landscaping parts (paving, fencing and share etc.) "network partners" have forgotten by the architect can then be recommended. It found there for lay not so easily sensible partner.
error:
- The plan was not ideal to put the split unit below the bedroom window. Even with the incoming air, it is good to hear. It seems that you get used to it, but otherwise it would have been better. Unfortunately this was not indicative of the planners.
- We would have a lot of bickering and 2 best Solutions spared if we had been to a union determined and would immediately require a different craftsmen. Too bad, but it's still turned out well.
- We should have respect cistern and wells are being advised, etc..
recommendations:
- The daylight spot is great.
- The Drempelerhöhung is highly recommended - at least if you build without a basement.
- allow plenty of outlets and LAN doses. You would not believe how quickly all of which are occupied.
- Who a convenient home automation looking for: Matic Home is great. We now have close to 60 actuators installed. Awesome - especially the price / performance ratio.
- For the heating briefing you should take plenty of time and rest. Otherwise, forget everything after 4 weeks.
- It is really recommended, Villeroy & Boch exhibition to visit. We are left with a priceless planning there. (Priceless good and, unfortunately, just as expensive) but it gave us in the bathroom planning helpful critical times and pointed out what is so everything.
- You should devote time for the planning of layout and functionality.
- Plant 10% for additional expenditure - even if you think you does not happen. Viebrock has of course to the fixed price, but you can find in the course of planning yet guarantee this and that, what is available at ...
Many thanks to ...
Viebrock (West) and the various squads of Wendt and other specialists who have worked, at
from Eßling & Son,
from Scheer Electric (Dormagen) ,
Mr Hasani ; (Dormagen) for the earthworks,
Hr. Grams of the oven Gallery (Dusseldorf) for the great fire planning and execution, the company
Pieczkowski (Meckenheim) for an immaculate and professional floor laying and
at www.my-haussteuerung.de, www . ehomeportal.de and the www.fhz-forum.de for help with our home automation
Viebrock:
happy again at any time! Very happy with Mr. Biesen, our consultant in Kaarst. Very happy again with Mr. Löhden, our construction manager. stress-free as we can with Viebrock, not build it, I say. The construction period
is phenomenal. The quality is great - if we as the layman can judge at this time. Any trouble and when it is going to be resolved were issues, so these were done without a lot of discussion of Viebrock. Great support from Viebrock - even after acceptance (at least so far). The architects are part of the process must clearly high -
: *
suggestions for Viebrock. We were there just before the contract cancellation.
- The heating instruction should include a brief pamphlet in which the 10 most important points are summarized. The components of the heaters are indeed quite uniform and thus the cost of Viebrock clear. The benefit would be our opinion but high.
- It would be great if Viebrock for the landscaping parts (paving, fencing and share etc.) "network partners" have forgotten by the architect can then be recommended. It found there for lay not so easily sensible partner.
error:
- The plan was not ideal to put the split unit below the bedroom window. Even with the incoming air, it is good to hear. It seems that you get used to it, but otherwise it would have been better. Unfortunately this was not indicative of the planners.
- We would have a lot of bickering and 2 best Solutions spared if we had been to a union determined and would immediately require a different craftsmen. Too bad, but it's still turned out well.
- We should have respect cistern and wells are being advised, etc..
recommendations:
- The daylight spot is great.
- The Drempelerhöhung is highly recommended - at least if you build without a basement.
- allow plenty of outlets and LAN doses. You would not believe how quickly all of which are occupied.
- Who a convenient home automation looking for: Matic Home is great. We now have close to 60 actuators installed. Awesome - especially the price / performance ratio.
- For the heating briefing you should take plenty of time and rest. Otherwise, forget everything after 4 weeks.
- It is really recommended, Villeroy & Boch exhibition to visit. We are left with a priceless planning there. (Priceless good and, unfortunately, just as expensive) but it gave us in the bathroom planning helpful critical times and pointed out what is so everything.
- You should devote time for the planning of layout and functionality.
- Plant 10% for additional expenditure - even if you think you does not happen. Viebrock has of course to the fixed price, but you can find in the course of planning yet guarantee this and that, what is available at ...
Many thanks to ...
Viebrock (West) and the various squads of Wendt and other specialists who have worked, at
from Eßling & Son,
from Scheer Electric (Dormagen) ,
Mr Hasani ; (Dormagen) for the earthworks,
Hr. Grams of the oven Gallery (Dusseldorf) for the great fire planning and execution, the company
Pieczkowski (Meckenheim) for an immaculate and professional floor laying and
at www.my-haussteuerung.de, www . ehomeportal.de and the www.fhz-forum.de for help with our home automation
|
| The first snowman ;-) |
Sun so that we have Biesen our promise to Mr. held and completed the building blog with conclusions. ;-)
We are of course accessible by mail, should you have any questions. In addition, yes, the comment form is still active for a while. Perhaps even unpacked so desire and we write later about what the outside work.
Thank you for reading!
* However, we are still waiting for the TV of Viebrock. ^ ^ If I had read a blog that was donated as a thank you. ^ ^ (Or we were not good enough ...)
Russian Wresting Singlets
Where was I stopped?
Ah yes, the river .... Please
does not exclude the long silence that something was wrong with the building was in order.
We were with the move, the last work and job technically (end = stress) just full capacity. When it was over, even Christmas / New Year's Eve was at the door.
So, I hope you all had a happy new year! You "all the best for 2011! ;-)
But first things first ...
Am 16.11. got up at 8, a horde of guys moving around the corner. The informed me then too, after Steffi had started to clean house direction that the "2-day-parade" would mean according to plan, that will take place tomorrow still fine-tuning of the kitchen. The rest would be done today, of course. Ha-ha ... actually you would have to be happy so ...
At the time, we always relaxed painters were still at various sites in the door to swing and the bricklayers spread the fire in 1000 disassembled parts in half the living room. Aaaaaaahhrg! (Think of this face in front of Kevin at home alone!)
To make it short. It was incredibly stressful, but everything went well. As it has always worked. It worked and we fell against 23 clock in our new bed in your new home! THE Had we not at 8 clock have thought possible. Again, many thanks to moves King, who did a great job. There is nothing broke.
had In the days after the painters are still working diligently. Also, our electrician had to do things. Suitable for Christmas came our shower wall and our fridge. In between, a few lights were so
There are still some minor things that are open. But our confidence in the integrity of Viebrock is undimmed.
A conclusion reached in a separate post later. can
But we celebrate our first Christmas quite comfortably at home ... with log fire. Simply wonderful.
this week after only 8-12 weeks delivery time (grrrr), our guest sofa bed and the bathroom furniture be delivered and installed. We are so far inside completely.
So we can then concentrate fully on the following topics less directly at (when looking out the window) in front of us. For the outer region was no longer processed in 2010. Fence, driveway, patio & Co. are now being addressed by and by ...
neighbors
meantime, we met with mulled wine and New Year's Eve, the people in our street. A very nice and colorful group. They are also very good prospects.
Oh yes, speaking of "good prospects": One Day just before Christmas, held a Viebrock car with a trailer in front of our driveway. I was really surprised, because I'm wanting to us. Neee ... have the soil samples in our neighboring property, and probably put us over. Ui. It will be created as well as from March 2-3 more Viebrock houses. We look forward to it and the rest of the road also ... because of the short construction period. ;-))) Nene, on the sure nice people ... ^ ^
Ah yes, the river .... Please
does not exclude the long silence that something was wrong with the building was in order.
We were with the move, the last work and job technically (end = stress) just full capacity. When it was over, even Christmas / New Year's Eve was at the door.
So, I hope you all had a happy new year! You "all the best for 2011! ;-)
But first things first ...
Am 16.11. got up at 8, a horde of guys moving around the corner. The informed me then too, after Steffi had started to clean house direction that the "2-day-parade" would mean according to plan, that will take place tomorrow still fine-tuning of the kitchen. The rest would be done today, of course. Ha-ha ... actually you would have to be happy so ...
At the time, we always relaxed painters were still at various sites in the door to swing and the bricklayers spread the fire in 1000 disassembled parts in half the living room. Aaaaaaahhrg! (Think of this face in front of Kevin at home alone!)
To make it short. It was incredibly stressful, but everything went well. As it has always worked. It worked and we fell against 23 clock in our new bed in your new home! THE Had we not at 8 clock have thought possible. Again, many thanks to moves King, who did a great job. There is nothing broke.
had In the days after the painters are still working diligently. Also, our electrician had to do things. Suitable for Christmas came our shower wall and our fridge. In between, a few lights were so
There are still some minor things that are open. But our confidence in the integrity of Viebrock is undimmed.
| |
| copied from Rina & Paddy. Thank you! |
A conclusion reached in a separate post later. can
But we celebrate our first Christmas quite comfortably at home ... with log fire. Simply wonderful.
this week after only 8-12 weeks delivery time (grrrr), our guest sofa bed and the bathroom furniture be delivered and installed. We are so far inside completely.
| |
| cinema |
|
| guest rooms / Zockzimmer |
| |
| bedroom |
| |
| living |
| |
| living room |
| |
| dining room / kitchen |
|
| the new refrigerator from Samsung |
|
| hallway |
So we can then concentrate fully on the following topics less directly at (when looking out the window) in front of us. For the outer region was no longer processed in 2010. Fence, driveway, patio & Co. are now being addressed by and by ...
| |
| South / East |
| |
| East |
| |
| South / West |
neighbors
meantime, we met with mulled wine and New Year's Eve, the people in our street. A very nice and colorful group. They are also very good prospects.
Oh yes, speaking of "good prospects": One Day just before Christmas, held a Viebrock car with a trailer in front of our driveway. I was really surprised, because I'm wanting to us. Neee ... have the soil samples in our neighboring property, and probably put us over. Ui. It will be created as well as from March 2-3 more Viebrock houses. We look forward to it and the rest of the road also ... because of the short construction period. ;-))) Nene, on the sure nice people ... ^ ^